PART SUBMISSION WARRANT (PSW)
The Part Submission Warrant or PSW is a document that summaries the whole ‘PPAP Package’. It needs to include details such as:
1) Part Information
2) Suppliers Contact Information
5) Reason for Submission
ii. Engineering Changes
iii. Tooling: Transfer, Replacement, Refurbishment, or Additional
iv. Correction of Discrepancy
v. Tool Inactive > 1 Year
vi. Change to Optional Construction or Material
vii. Supplier or Material Source Change
viii. Change in Part Processing
ix. Parts Produced at Additional Location
x. Other (Specify)
6) Requested Submission Level
ii. Level 2 – Warrant with product samples and limited supporting data
iii. Level 3 – Warrant with product samples and complete supporting data
iv. Level 4 – Warrant and other requirements as defined by customer
v. Level 5 – Warrant with product samples and complete and complete supporting data reviewed at suppliers manufacturing location.
7) Submission Results
ii. Material and function tests
iii. Appearance Criteria
iv. Statistical process package
9) Explanations or Comments
The Part Submission Warrant or PSW is a document that summaries the whole ‘PPAP Package’. It needs to include details such as:
1) Part Information
- Part Name
- Part Name on Drawing
- Engineering Change Level
- Engineering Change Date
- Additional Engineering Changes
- Additional Engineering Changes Date
- Safety and/or Government Regulation
- Checking Aid Number
- Checking Aid Engineering Change Level
- Checking Aid Engineering Change Date
- Customer Part Number
- Organization Part Number
- Purchase Order Number
- Weight
2) Suppliers Contact Information
- Name of Supplier and/or Vendor Code
- Suppliers Address
- Customers Name and Division
- Any buyer code
- Substance of Concern Information
- IMDS format
- IMDS ID
5) Reason for Submission
- There can be many reasons why it is necessary to conduct a PPAP :
ii. Engineering Changes
iii. Tooling: Transfer, Replacement, Refurbishment, or Additional
iv. Correction of Discrepancy
v. Tool Inactive > 1 Year
vi. Change to Optional Construction or Material
vii. Supplier or Material Source Change
viii. Change in Part Processing
ix. Parts Produced at Additional Location
x. Other (Specify)
6) Requested Submission Level
- There are different levels of PPAP submission
ii. Level 2 – Warrant with product samples and limited supporting data
iii. Level 3 – Warrant with product samples and complete supporting data
iv. Level 4 – Warrant and other requirements as defined by customer
v. Level 5 – Warrant with product samples and complete and complete supporting data reviewed at suppliers manufacturing location.
7) Submission Results
- Have you included results for:
ii. Material and function tests
iii. Appearance Criteria
iv. Statistical process package
- Do all the results meet all the design requirements with any concerns noted
- Mold / Cavity / Production Process ID
9) Explanations or Comments
- Comments / Explanations
- Customer tool tags
- Signature
- Date
- Printed name
- Phone Number
- Fax Number
- Job Title